GK Irrigation Pumping Station - Civil & Building Works :  
   
GK Irrigation Pumping Station under Japan Debt Relief Fund in Kushtia  
Civil & Building Works on Turn-key basis involving  
Construction of Concrete lined Main Distribution Canal, Internal Road,  
Boundary-wall, Stock-pile Area for Treating Dredged Silts,  
Deep Water Wells (3 Nos.) for Industrial Water, Overhead Water Tank,  
Rehabilitation of Intake Structure and Irrigation Pumping Station with Electrical Lighting,  
Water Supply & Sewage Systems  
   
Client: Ebara Corporation, Japan  
Owner: Bangladesh Water Development Board  
   
 
 
 
 
   
    GK Irrigation Pumping Station - Mechanical & Electrical works :  
   
GK Irrigation Pumping Station under Japan Debt Relief Fund in Kushtia  
Project work included Mechanical & Electrical works involving  
Assembly and Installation of Intake Control Elements (Sluice Gate,  
Stop-log & Bar screen), Installation of Sluice Gate Lifting Cranes,  
Installation of 3 Nos. 1,700m3/min. Axial-flow Pumps (2,800KW each),  
Instrumentation & Control System, Data-logger,  
Flow Measuring Device, Fire Detection System,  
Electrical Distribution & Receptacles System, Dredging Pump Barge,  
25t EOT Crane and Trash Rake Car/ Crane  
   
Client : Ebara Corporation, Japan  
Owner : Bangladesh Water Development Board  
   
 
 
 
 
   
   
    Mymensingh Power Station (Phase-I) 2X35MW Gas Turbine (GE Frame-6) :  
   
Mymensingh Power Station (Phase-I): 2X35MW Gas Turbine (GE Frame-6)  
Project works involved :  
 
Civil & Architectural works on Turn-key basis involving Land Reclamation, & Site Filling & Compaction, Slope Protection Work with Geo-textile and Gravel baskets, Construction of Internal Road with side-walks, Boundary Fencing, Water Supply, Storm Water & Sewage Networks, Plant Site Main Switch Yard & Sub-station (11KV/132KV), City-end Grid Sub-station Extension, Pipe & Cable Rack, Cable Trench, Gas Pipe Trench, Make-up Deep Water Wells (3 Nos.), Gas Turbine (2X35MW, GE Frame-6) & Generator Barge Foundation, Fire Annunciation & Fire Fighting System, Main Warehouse & Workshop Building, Main Office Building, Engineer¡¯s Accommodation Building, Car Parking Sheds, Gate House & First Aid Station, Security Guard¡¯s Accommodation Building, Barge Access Canal & Plant Access Road from Highway (1.2KM), Black Start Generator, Plant Area Lighting and Landscaping
 
   
Client : Consortiums of MES Engineering & Shipbuilding Co. Ltd. (MES), Japan & European Gas Turbines (EGT), France  
Owner : Rural Power Company Limited  
   
 
 
 
 
 
   
    Mymensingh Power Station (Phase-II) 2X35MW Gas Turbine (GE Frame-6) :  
   
Project works involved :  
 
Civil & Building Works on Turn-key basis involving Land Reclamation, Site Filling & Compaction, Slope Protection and Construction of Internal Roads, Storm Water System, Boundary Fencing, Pipe & Cable Rack, Cable Trench, Gas Pipe Trench and Rack, Gas Turbine (2X35MW, GE Frame-6) & Generator Foundation, Switch Yard & Sub-station (3X50MVA, 11KV/132KV),
 
Overland Transportation Work : Gas Turbine (100 Tons each) & Generator (110 Tons each). From Kanchpur, Dhaka to Plant Site at Mymensingh which included Transportation of the consignment using a 96-wheeled Flat-bed Trailer
 
   
Client : GE Energy Products, Europe (GEEP), Europe, Belfort, France.  
Owner : Rural Power Company Limited  
   
 
 
 
 
   
Copyright© TECHNO-CON
 
Designed & Developed by DesignDesk
 
GK Irrigation Pumping Station
- Civil & Building Works
 
GK Irrigation Pumping Station
- Mechanical & Electrical works
 
Mymensingh Power Station (Phase-I) 2X35MW Gas
Turbine (GE Frame-6)
 
Mymensingh Power Station (Phase-II) 2X35MW Gas Turbine (GE Frame-6)